R.L. Mlazgar Associates, a Minnesota lighting representative agency, currently owes Hubbell Lighting about $9.25 million, and it is asking the Fourth Circuit to delay collection while it challenges the verdict. HLI Solutions, the former Hubbell Lighting now part of Current, urged the appeals court on Thursday to turn that request down.
Judge Jacquelyn D. Austin entered judgment on August 31 awarding Hubbell Lighting $10,724,878 on its breach of contract counterclaim. Mlazgar recovered $1,478,848 under South Carolina's sales representative statute, half of it punitive, leaving the agency with a net obligation of roughly $9.25 million.
Two requests on a lapsed clock
The automatic 30-day hold on collection expired October 1. Mlazgar asked Judge Austin in September to extend it and has received no ruling. On November 3 the agency took the matter to Richmond, seeking to block collection until February 18, 2027, and to file its balance sheet under seal.
Mlazgar offers two grounds. A fee petition seeking $3,843,818 and a request for $319,616 in prejudgment interest remain pending in Greenville and could shrink the net figure. Separately, the agency goes to trial January 19 in Minneapolis against Focal Point, where its lawyers say a large recovery could help it post security.
Hubbell Lighting dismissed the warnings about Mlazgar's finances as an assertion offered with no proof. It relied on a 2010 South Carolina ruling that refused a stay despite the debtor's claimed inability to pay, warning that a judgment holder should not be left to fund an appeal on an unsupported hope of later payment.
Trial exhibits show a smaller book
Records from the August trial make that hope look thin. In 2019, the last full calendar year before the dispute, Mlazgar and Elan Lighting, the Wisconsin agency Mlazgar later acquired, represented Focal Point and sister company Kenall. Those two lines generated roughly $333,000 and $149,000 in commissions. In the same year Mlazgar earned approximately $941,000 representing Hubbell Lighting.
Even a Minneapolis award equal to one to three years of those Focal Point and Kenall commissions would land between the mid six figures and the low seven figures, a small share of what the agency owes Hubbell. The comparison describes a book about half the size of the one that produced the verdict against Mlazgar.
A rare shortcut request
Alongside the stay, Mlazgar filed a motion for summary reversal, a procedure that lets an appellate court discard a judgment without full briefing when the issues are manifestly unsubstantial. Courts typically use it where precedent has already settled a question. Mlazgar is asking for it after a nine-day jury trial and a $10.7 million verdict.
The agency argues the exclusivity clause it breached is an unenforceable non-compete under South Carolina law, and that a separate contract provision bars Hubbell Lighting's lost-profit damages. Hubbell Lighting calls the motion meritless and bordering on frivolous, says the district court rejected the liability argument three times, and notes that Mlazgar cited no case from any circuit summarily reversing a jury verdict.
The Cooper deck and causation
A slide deck dated October 9, 2020, sits at the center of the causation fight. Five weeks before Mlazgar's agency announced it was taking on Cooper Lighting, then-Cooper executive Shane Bickley emailed it under the subject line “Mlazgar Rollout.” One slide carried the heading “Conversion of Hubbell business from prior Mlazgar relationships.” The plan laid out a 30-day launch, including a step to convert Hubbell stock positions at Mlazgar strongholds, a market push aimed at the top 20 contractors, distributors and specifiers with an emphasis on customers holding existing Hubbell Lighting projects, and a promotion to speed conversions away from Hubbell.
Hubbell Lighting filed the deck under seal in Greenville last month; in Richmond it sits on the public docket. Hubbell uses it to rebut Mlazgar's claim that the breach did not cause the lost profits, writing that the agency and Cooper were planning those losses before the breach occurred.
What comes next
Mlazgar can reply before a three-judge panel takes up the stay. The panel could grant a temporary pause, deny it, or leave the matter to Judge Austin, who has held the September request for eight weeks. Inside Lighting sought comment from the agency's attorneys on the afternoon of November 12; only automated replies arrived before publication.
For lighting manufacturers and their representatives, the case sharpens a practical question: what it costs to end an agency agreement, and who absorbs the loss when a line changes hands.